| dc.identifier.citation | Merter, A., & Albayrak, G. (2025). İnşaat Projelerinde Süre Uzatımının Hukuki ve Mühendislik Açılardan İncelenmesi. Afyon Kocatepe Üniversitesi Fen Ve Mühendislik Bilimleri Dergisi, 25(4), 878-902. https://doi.org/10.35414/akufemubid.1587364 | en_US |
| dc.identifier.uri | https://dergipark.org.tr/tr/download/article-file/4375662 | |
| dc.identifier.uri | https://hdl.handle.net/11630/13100 | |
| dc.description.abstract | İnşaat sözleşmelerinde genel itibariyle, yüklenicinin taahhüt
ettiği edimi yerine getirmesi için bir süre belirlenmektedir.
Belirlenen inşaat süresi uzadıkça, işin tamamlanamama ihtimali
de artmaktadır. Ülkemizde de inşaat projelerinin sıklıkla
vadesinde bitmediği, bu durumda yüklenicilerin cezalı şekilde
çalıştığı ya da sözleşmenin feshi ile karşı karşıya kalındığı
bilinmektedir. En sıradan bakım-onarım işlerinden, daha
karmaşık ve uzmanlık gerektiren hastane, okul, altyapı işlerine
kadar her türden projenin teslim süresi hususunda yüklenici
firma ile sorunlar yaşanabilmektedir. Bu noktada gecikmeye
neden olan etkenlerin ortaya konulması önem kazanmaktadır.
Çünkü bu şekilde yüklenici temerrüde düşebileceği gibi işin
bitirilmesi için süre uzatımı hakkı da kazanabilmektedir. Süre
uzatımına ilişkin talepler çoğu zaman taraflar arasında
anlaşmazlıklar yaratmakta, bu durum hukuki süreçlerin
uzamasına ve projenin aksamasına neden olmaktadır. Bu
çalışmada özel sektörde 6098 Sayılı Türk Borçlar Kanunu
hükümlerine tabi şekilde imzalanan inşaat sözleşmelerinde süre
uzatımı kavramı ele alınmaktadır. Bu amaçla, ilgili mevzuatlar
incelenmiş, sözleşme taraflarının sorumlulukları ve süre
uzatımının koşulları ile hesabına yönelik hem hukuki hem de
mühendislik çözümlerine yer verilmiştir. Ayrıca inşaat işlerinde
uygulanan iş programı ve gecikme analizleri aracılığıyla süre
uzatımı değerlendirilmiştir. | en_US |
| dc.description.abstract | In construction contracts, a specific due date is generally set for
the contractor to fulfill the obligations they have committed to.
As the construction period extends, the likelihood of the project
not being completed increases. It is well-known that in our
country, construction projects frequently fail to be completed
on time, which often results in contractors working under
penalties or facing contract termination. The problems can arise
regarding the completion time of all types of projects, ranging
from the routine maintenance and repair tasks to more complex
and specialized projects such as hospitals, schools, and
infrastructure works. At this point, it becomes crucial to identify
the factors causing the delays since the contractor may fall into
default or, alternatively, gain the right of a time extension for
completing the work. The requests for time extensions
frequently lead to disputes between the parties, prolonging
legal processes and causing project delays. In this study, the
concept of time extension in construction contracts signed in
the private sector under the provisions of the Turkish Code of
Obligations No. 6098 is examined. For this purpose, relevant
laws have been reviewed, and both legal and engineering
solutions are provided concerning the responsibilities of the
contracting parties, the conditions for time extension, and how
it is calculated. Additionally, time extension is evaluated through
project schedules and delay analyses used in construction
projects. | en_US |
| dc.language.iso | tr | |
| dc.publisher | Afyon Kocatepe Üniversitesi | en_US |
| dc.relation.ispartof | Fen ve Mühendislik Bilimleri Dergisi | |
| dc.identifier.doi | 10.35414/akufemubid.1587364 | |
| dc.rights | info:eu-repo/semantics/openAccess | en_US |
| dc.subject | Construction Contract | en_US |
| dc.subject | Time Extension | en_US |
| dc.subject | Construction Law | en_US |
| dc.subject | Project Schedule | en_US |
| dc.subject | Delay Analysis | en_US |
| dc.subject | İnşaat Sözleşmesi | en_US |
| dc.subject | Süre Uzatımı | en_US |
| dc.subject | Eser Hukuku | en_US |
| dc.subject | İş Programı | en_US |
| dc.subject | Gecikme Analizi | en_US |
| dc.title | İnşaat projelerinde süre uzatımının hukuki ve mühendislik açılardan incelenmesi | en_US |
| dc.title.alternative | Examination of time extension in construction projects from legal and engineering perspectives | en_US |
| dc.type | Article | |
| dc.department | Seçiniz | en_US |
| dc.identifier.orcid | 0009-0007-5997-8045 | en_US |
| dc.identifier.orcid | 0000-0001-6114-4292 | en_US |
| dc.identifier.volume | 25 | en_US |
| dc.identifier.startpage | 878 | en_US |
| dc.identifier.endpage | 902 | en_US |
| dc.identifier.issue | 4 | en_US |
| dc.relation.publicationcategory | Makale - Ulusal Hakemli Dergi - Başka Kurum Yazarı | en_US |